Multi-year storm sewer replacement on Notre-Dame Street in Embrun. Consult the presentation slides and view projects updates and notices below to stay up to date on this project.
View Presentation Slides HereThe Township of Russell would like to thank residents, businesses, and visitors for their continued patience and cooperation as reconstruction work continues along Notre-Dame Street.
Construction activities have continued to progress eastward, and additional traffic control changes are planned over the coming weeks as crews advance through the next phase of underground infrastructure work.
Crews are currently working on Notre-Dame Street between the Notre-Dame / St-Pierre / Ste-Marie intersection and Dignard Street, including the installation of underground watermain and storm sewer infrastructure.
Temporary watermain installation is expected to begin next week east of Dignard Street as preparations continue for the next phase of construction.
The contractor will continue to communicate directly with affected businesses and property owners as construction activities approach their properties.

Over the next two weeks, construction activities are expected to continue progressing eastward toward the Dignard Street intersection.
To help maintain access to local residences and businesses while work progresses, traffic control measures near Dignard Street will be adjusted in stages.
As construction reaches the Dignard Street intersection, the intersection of Dignard Street and Notre-Dame Street will be temporarily closed while underground infrastructure work is completed.
During this period:
Following completion of the intersection work, it is anticipated that:
This staged approach is intended to maintain local access while allowing construction activities to continue progressing eastward along the corridor.
The Township and contractor remain committed to maintaining access to local businesses whenever feasible throughout construction.
Businesses will continue to receive direct communication from the contractor as work approaches their properties. Temporary adjustments to entrances, sidewalks, patios, parking areas, and vehicle access may be required while work is taking place immediately adjacent to certain businesses.
Pedestrian access to businesses will remain available whenever possible.
As on-street parking remains unavailable within active construction areas, residents and visitors are encouraged to use nearby public parking locations, including:
Parking availability is limited and users are encouraged to follow all posted signage and restrictions.
We understand that construction can be disruptive and sincerely appreciate the patience, understanding, and cooperation of residents, businesses, and visitors.
These infrastructure upgrades will provide significant long-term improvements to water, stormwater, transportation, and pedestrian infrastructure throughout the community.
For questions or concerns, please contact the Township at 613-443-1747 or infrastructure@russell.ca.
Here is your weekly construction update for Notre-Dame Street. Local businesses remain open and accessible.
West-side access (Ste-Marie/St-Pierre)
• Jean Coutu
• Medical Clinic
• Max Athletics
• Treasureland Liquidation
• Feetures
• Embrun Vape Store & Smoke
• Pretty Lash Bar & Spa
• Andrew’s Barbershop
• Bijoutier Longtin
• Salons Funéraires Laurent Hill Funeral Homes Ltd.
• Loiselle Sports
• Point S City – Garage Loiselle & Autoglass
East-side access(Blais)
• Euphie d’ici – Café & smoothie bar
• Fournier RE Group, Royal Lepage Performance
• Homestead Pub
• Marcil Lavallée
Not accessible by car
• Embrun Asian Express (Closed July 6-Aug 6)
The following businesses remain open and accessible:
• Embrun Home Hardware Building Centre
• All Out Burger
Parking available in the construction zone

While road work continues on Notre-Dame Street, we would like to remind residents that businesses remain open and accessible during construction.
Most businesses can currently be accessed from the east side near Blais Street. Residents may also drive through the construction zone to access businesses or residences located within the work area. Please drive slowly and follow all posted signs and directions from workers to help keep everyone safe.
As construction progresses eastward, access to businesses will gradually shift to the west side. We will provide weekly updates indicating which businesses can be accessed from each end of the construction zone.
Parking is available at the following locations:
We encourage residents to continue supporting local businesses during construction and thank you for your patience and understanding.
The Township reminds residents to respect all traffic control devices in the Notre-Dame Street construction area. We have been informed that barrels, barricades, cones and signs are being moved by members of the public. These devices are in place for the safety of everyone. Moving them can create unsafe conditions for drivers, pedestrians and construction workers. Please do not move any traffic control devices.
Residents are also reminded to follow posted detours. Voyageur Street should not be used as a shortcut, as it is a one-way street at the southern end. The official detour is through Route 400.
Businesses in the area remain open and accessible. The Township encourages residents to continue supporting local businesses during construction.
At this time, access is from the east (at Blais Street). You may drive slowly through the construction zone if going to a business or residence in the zone. As construction progresses to the east, access points will shift gradually and access from the west will be reintroduced to maintain local access to properties at that end of the zone.
Due to the nature of the work, it is not possible to confirm in advance when access will change for each property. The contractor, Coalwater, will continue to communicate directly with affected businesses and residents to provide notice of any changes.
We thank residents and businesses for their patience and cooperation.
The paving work on Ste-Marie Road and St-Pierre Street is almost complete, and the roads will reopen to traffic at 6:30 a.m. on Monday, June 22.
Crews are continuing with the Notre-Dame Street Rehabilitation Project and moving into the next phase of sewer work.

Notre-Dame Street, from Ste-Marie Road to Blais Street, will be closed on Monday June 22, 2026, at 6:30 a.m. for the next few months.
We understand this closure will have a significant impact on residents, businesses and daily travel. However, a full road closure is necessary to complete the work safely and as quickly as possible. We appreciate the community’s patience and cooperation during this time and remind everyone to follow the posted detour routes and allow extra time for travel.
The Township of Russell will continue to share updates as more information becomes available. For full project details, visit www.russell.ca/NotreDameSt. If you have questions, contact the Infrastructure Department at infrastructure@russell.ca or 613‑443‑1747.
Construction continues on the Notre-Dame Street Rehabilitation Project at the intersection of Notre-Dame Street, Ste-Marie Road and St-Pierre Street. Crews are progressing with the sewer work and are on to the next phase of the project.
Once paving is done and Ste-Marie and St-Pierre roads have re-opened, Notre-Dame Street from Ste-Marie Road to Blais Street will be closed for the next two months. We will send a road closure when an exact date is set.
The Township of Russell will continue to share updates as more information becomes available. For full project details, visit www.russell.ca/NotreDameSt. If you have questions, contact the Infrastructure Department or 613‑443‑1747.

The work on the Notre-Dame Street Rehabilitation Project at the intersection of Notre Dame Street and Ste Marie Road and St Pierre Street continues and we will be moving to the next step in the project.
The full intersection closure, which began on April 15, has now ended as of May 15, 2026.
The Township encourages residents to continue supporting local businesses in the affected area during construction.
The Township of Russell will continue to share updates as more information becomes available. For full project details, visit www.russell.ca/NotreDameSt. If you have questions, contact the Infrastructure Department or 613 443 1747.

The work on the Notre-Dame Street Rehabilitation Project at the intersection of Notre-Dame Street and Ste- Marie Road and St-Pierre Street is progressing well. However, due to site conditions encountered, adjustments to the project timeline are required as we move into the next phase.
The full intersection closure, which began on April 15, will be extended by approximately one additional week. We will provide further updates as they become available.
The Township encourages residents to continue supporting local businesses in the affected area during construction.
Short water interruptions may be required during this period. Affected residents will be notified in advance, where possible, with further details.
The Township of Russell will continue to share updates as more information becomes available. For full project details, visit www.russell.ca/NotreDameSt. If you have questions, contact the Infrastructure Department or 613‑443‑1747.

The Township of Russell is providing more information about the road closure at the intersection of Notre-Dame Street and Ste-Marie/St-Pierre Roads related to ongoing construction.
The included map shows the full intersection closure, that began April 15 and is expected to last until approximately May 8, 2026. This timeline may change if unforeseen construction issues or previously unknown underground infrastructure are discovered.
A full intersection closure is required to complete most, if not all, of the underground infrastructure work at this location. The contractor will make every effort to complete as much work as possible during this period so construction can then move to the roadway approaches.
Thank you for your patience and cooperation. For questions on the project contact the Infrastructure Department or at 613-443-1747.
Construction for the Notre-Dame Street Rehabilitation Project began in early March and is progressing as planned. Project partners have confirmed that work will continue along Ste-Marie Road, moving toward Notre-Dame Street.
Over the past several weeks, the construction schedule and the complexity of several work elements were carefully reviewed. Based on this review, a full closure of the intersection at Notre-Dame Street and Ste-Marie and St-Pierre Roads was identified as the safest and most efficient option to complete the next phase of work.
Once work at the intersection is finished, construction will continue in both directions along Notre-Dame Street. Some localized road closures will remain in place to avoid overlapping trench work and to reduce traffic delays.
Residents and road users are encouraged to subscribe to email notices at www.russell.ca/subscribe, to follow the project page at www.russell.ca/NotreDameSt and to consult Municipal 511 for the most up to date information on detours and traffic impacts.
The Township of Russell thanks residents and businesses for their patience and cooperation while this important infrastructure project moves forward.
Please take note of the following alternating lanes:
Traffic is alternating in both directions, controlled by temporary traffic lights on Ste-Marie Road, between Notre-Dame Street and Castor River. Expect delays and please follow signals and on-site instructions.
Please see the map from www.Municipal511.ca for detour information.
The Township of Russell invites you to attend a Public Information Session regarding Phase 2 of the Notre Dame Street Storm Sewer Replacement and Rehabilitation Project. This is the second phase of the multi-year project.
The tender for Phase 2 was awarded to the General Contractor and construction is expected to begin within the next month and will take approximately two years to complete. The construction limits for Phase 2 include:
We appreciate your cooperation and encourage you to participate in the Public Information Session to ask questions and share your feedback early in the process.
If you cannot attend the Public Information Session, you may send any questions to our Infrastructure Department. The information from the information session will be added to www.russell.ca/NotreDameSt a week before the information session. We invite you to review them ahead of the meeting and come prepared with your questions.
As you may have seen, Notre-Dame Street is now fully open to traffic!
Phase 1 of this 5-phase project is now complete, and we want to extend a big thank you to all residents and local businesses in the affected area for their patience and understanding throughout the work.
More information about Phase 2, planned for next summer, will be shared as soon as it becomes available.
Thank you for your continued cooperation!
Ontario investing $9.6 million in the Township of Russell to enhance the water and storm system
Please see the map from www.Municipal511.ca
The Township Council has approved a contract with Coalwater Excavation Inc. to proceed with the replacement of storm water sewers on Notre-Dame Street. This work is necessary to upgrade aging infrastructure, improve drainage, and to be more resilient to the climate change.

We encourage you to visit the Municipal 511 website (www.municipal511.ca) for updates regarding construction, road closures, and detour information. This service provides a map-based road information system to keep the community informed.
The replacement of the storm water sewers includes:
The project will be completed in three key stages, as outlined below:
Construction may cause vibrations due to heavy compaction and driving equipment. In rare cases, this can lead to damage to structures or contents.
To document existing conditions, Englobe Engineering—a sub-consultant to Coalwater Excavation Inc.—will conduct a pre-condition survey starting June 3rd, 2025, and continuing over the following weeks. This survey would include photographic and/or video documentation to assist with potential claims.
property owners will receive formal notification regarding the pre-condition survey. If a property is leased or rented, it is the property owner’s responsibility to inform their tenants about this process.
Tenants should be aware that Englobe Engineering may need access to properties for inspection purposes. If tenants have concerns or require further information, they should coordinate with their landlord or directly reach out to the contractor.
During construction, some properties will experience temporary disruptions to water service due to necessary water works. To ensure uninterrupted access to potable water, the Contractor will provide temporary water supply connections to affected residences and businesses.
Temporary potable water supply will be connected via a wye at an outside tap or to the existing water service.
Property owners and businesses should contact the contractor directly to communicate any special water supply requirements beyond these standard measures. Additionally, written notices will be provided at least 48 hours before any planned disruption to water service.
If you experience any changes in water pressure or have concerns about water quality, please contact the Township of Russell as soon as possible to report the issue.
For further information regarding water service interruptions, please contact:
Carl Charbonneau
Estimator, Project Manager
Coalwater Excavation Inc.
613-324-3378
If you have any questions or concerns regarding this project, please contact Coalwater Excavation Inc. directly or reach out to the Project Manager from the Infrastructure Department at the Township of Russell or 613-443-1747.
We appreciate your patience and cooperation as we work to improve the infrastructure in your community.
Council awarded the first contract to Coalwater Excavation. Construction is expected to begin at the end of June. More details about the timeline and road closures will be shared as they become available.
View the Council Meeting agenda for more details.
The Township of Russell invites you to attend an upcoming Public Information Session regarding proposed improvements to Notre-Dame Street. If you are the landlord, we kindly ask that you inform your tenants about this upcoming session to ensure everyone is aware and has the opportunity to attend.
This session will be held in a drop-in format, allowing you the flexibility to stop by at your convenience.
At the session, you will have the opportunity to speak directly with Township staff and project team members, ask questions and share feedback.
Please note that while the full project will be presented during the session, only Phase 1 (from Blais St. to 964 Notre-Dame St.) is scheduled to proceed to construction this year. The remaining phases are planned for future years, as part of a multi-stage approach.
We encourage everyone to join us, learn about the project, and share your thoughts! If you are unable to attend but would like more information, please contact us our Infrastructure Department and we will send you the information package once it is available for public review.
Sincerely,
Infrastructure Services
717 Notre-Dame St, Embrun ON K0A 1W1
Call: 613-443-3066
Contact Us
Departmental Directory
© 2026 Municipalité de Russell Township
© 2026 Municipalité de Russell Township